Fig. 50: Preferred installation for liquids
I DPT10
II 3-fold valve block
III Precipitator
1.5 Drain valves
2.4 Inlet valves
3 Breather valve
6, 7 Vent valves on DPT10
A, B Blocking valves
Proceed as follows:
1 Close valve 3
2 Fill measuring system with medium.
Open valves A, B, 2, 4: Medium ows in.
If necessary, clean the dierential pressure lines: - with gases by
blowing out with compressed air - with liquids by rinsing.
5)
Close valve 2 and 4, block the instrument
Open valve 1 and 5
Close valve 1 and 5
3 Remove air from instrument:
Open valves 2 and 4: Medium ows in
Close valve 4: Minus side will be closed
Open valve 3: Equalisation plus and minus side
Briey open valve 6 and 7, then close again: Fill the measuring
instrument completely with the medium and remove air
4 Put measurement loop into operation:
Close valve 3: Separate plus and minus side
5)
Arrangement with 5 valves.
Installation for liquids
Prepare the adjustment
66 Dierential pressure transmitter DPT10 - metal measuring diaphragm F oundation Fieldbus