Fig. 46: Preferred installation for open vessels
I DPT10
II Precipitator
1 Drain valve
6.7 Vent valves on DPT10
A Blocking valve
Proceed as follows:
1 Fill the vessel to just over the lower tap.
2 Fill measuring system with medium.
Open valve A: Medium flows in.
3 Vent instrument
Briefly open valve 6, then close it: Fill the measuring instrument
completely with the medium and remove air.
4 Set measurement loop to operation
Now:
Valve A open and valve 6 closed
Then carry out adjustment, see below.
Installation for open
vessels
Prepare the adjustment
62 Differential pressure transmitter DPT10 - metal measuring diaphragm • F oundation Fieldbus
8 Set up
37246-EN-100120